Microsoft Project Test

Exam Type: Microsoft Project MCQ Skill Test
Questions Type: Multiple Choice Questions
Total Questions: 30
Time Limit: 30 Minutes
Last Update June, 2025

Pass Microsoft Project Exam

75%
Total time

1 minute 2 seconds

Total time

1 correct answers

Total time

6 incorrect answers

Total time

6 not attempted

Start

Microsoft Project Quiz

Question 1 of 30
30:00

In the image below, what does the indicator in Task ID 9 represent?

Gantt Chart view of task list. Item 9 has a document icon next to it.

  • custom field
  • resource pool
  • linked file
  • subproject
     

What Microsoft Project view is shown in the image below?

Project stages represented by text boxes connected with arrows

  • Flow Chart
  • Gantt Chart
  • Task Dependency Report
  • Network Diagram
     

Where can you set fixed duration, effort driven, and manually scheduled????

You would like the ability to edit your typed entries in the Entry Bar, which appears below the ribbon and above the default Entry table in the Gantt Chart view. You recently received a new computer and noticed that the Entry Bar is missing. How do you fix this?

Which of the following defines the project scope in terms of deliverables and components, and provides the framework on which the project status is based?

When setting the Calculate multiple critical paths option in a master project's Advanced settings, which statement is correct?

You want to switch the scheduling mode for a project from scheduling from a start date to scheduling from a finish date. This action will change the default constraint from As Soon As Possible to As Late As Possible. Which dialog box should you use to make this change?

A project contains many elements. What is used to describe the sum of the work required?

Which option is not available in the Report tab on the ribbon?

You are troubleshooting a schedule on someone else's computer. The schedule has 10,000 tasks. When a change is made to a task's duration on a Fixed Units task, the start and finish dates do not change, change highlighting does not appear, and the Gantt Chart bar does not update. What is the cause of this issue?

You would like to understand which tasks are critical and which are not. When looking at the Gantt chart, how are these tasks identified by default????

You are working on a project that has tasks with no flexibility. Which constraint type offers no flexibility?

In a project, duration can have different units. Which duration unit is not valid?

Microsoft Project uses calendars to schedule a project. Which project components can be assigned a calendar?

You are working on a project file that contains many linked subprojects. When saving the files, what option can you use to immediately save the open files, including those that have not changed?

A resource is assigned to a task that is scheduled for 2 days. The resource is scheduled for 8 hours (8h) per day at 100%. The resource performs actual work of 10 hours on the first day. How has the Peak for this resource changed?

What is another name for a work breakdown structure?

A report for Earned Value Over Time has been requested. You decide to use a Microsoft Project visual report. What values does this report template compare when run?

You are preparing a meal comprising a main dish and multiple side dishes. You want the finish of the main dish to drive the finish of the side dishes. The main dish will start before and take longer than the side dishes. You need to create a link from the main dish to each of the side dishes. Which link type is appropriate?

A resource is overallocated in a project. This resource is responsible for two tasks that are to happen at the same time. The first of these tasks is on the critical path. Which solution should you use to remedy the overallocation?

How do you mark a task's progress and have that progress reflected in the task's summary task?

You have many tasks in a project file and want to convert them into milestones. How can you do this?

A project has been delayed by three months. In this project, you have set deadlines that also need to be delayed by three months. What feature should you use to accomplish both of these delays????

How many default base calendars does Microsoft Project set up for a project????

A task has a fixed duration If the units on the task are changed, what value for the task will automatically change as a result?Where can you set fixed duration, effort driven, and manually scheduled?

You are working with subproject files (the master project file is not open) and have saved the changes you made. What happens to the master project when it is opened????

You need to modify a resource pool. When opening the file that contains the pool, which of the following is NOT a valid option??

On your computer, Automatically add new views, tables, filters, and groups to the global is selected. You are using a custom filter that you created in one of your schedules, and you modify it to better meet your needs. You now notice that this modification is not available in other schedules. How do you fix this????

A graduated scale of rates can be created for a resource by using cost rate tables. What is the maximum number of cost rate tables each resource in a project have????

A project currently has a software developer performing two tasks at the same time. The first task is 5 days long; the second task is day long. It has been decided that the developer can take some time to work on the shorter task in the middle the longer task without impacting the schedule. What is the best way to this!

Microsoft Project Test Explained